Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 2) Environmental Permit no. EP-364/2009/B, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEP-07/364/2009/A and FEP-08/364/2009/A Monthly
Environmental Monitoring & Audit Report
- December 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
11 January 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. status of regulatory
compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review of the Reasons for and the Implications of
Non-compliance
6.5 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction
Impact due to the Concurrent Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of Individual Contracts under the
Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/17
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Table 3.5 Summary of submission status under
FEP-02/364/2009
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-01/364/2009
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/18
Table 3.9 Summary of submission status under
FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Table 3.11 Summary of submission status under
FEP-06/364/2009/A
Table 3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.15 Summary of submission status under
FEP-08/364/2009
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no.
HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no.
HY/2009/18
Table 5.3 Noise Monitoring Station for Contract no
HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no.
HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no.
HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for
Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for
Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no.
HY/2009/18
Table 5.10 Air Monitoring Station for Contract no.
HK/2009/01
Table 5.11 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.12 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no.
HY/2009/19
Table 5.15 Details of Waste Disposal for Contract no.
HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no.
HK/2009/02
Table 5.17 Details of Waste Disposal for Contract no.
HY/2009/18
Table 5.18 Details of Waste Disposal for Contract no.
HY/2009/15
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.20 Details of Waste Disposal for Contract no.
HK/2010/06
Table 8.1 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for
Contract no. HY/2009/19
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.4 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix
5.4 Real-time
Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
·
No
further work under designated project1
1Remarks: The construction of bored pile E3B under
FEP-03/364/2009 was confirmed completed and the bored pile E3B and the works
area was handover to contract
no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Pre-bored
H-piling
·
Bridge
construction
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
·
Backfilling
works on top of SCL protection works.
·
Jet
grouting to HKCEC new extension foundation.
·
Plant
mobilization for installation of pre-bored H-pile works at Stage 1b & Stage
2
·
Pre-drilling
works for CWB (Stage 2).
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Trimming
of pile head and blinding laying construction at WCR1 of Tunnel Portion 1
·
Waterproofing
installation at WCR1 of Tunnel Portion 1 Bay 2 - Bay 7 together with Bay 8 – Bay
16
·
Preparation
works for extract the western temporary sheetpile wall
·
Diaphragm
wall of panel P106, C107, P108, C109, P110, C111, P112, P114, C115 & P116.
Panel P113.
·
Preparation
works of saw cut Southern Diaphragm wall for the connection between existing
drainage and Bay 1 of Box Culvert N1.
·
Trial
excavation, Footpath Set back, UU Diversion and preparation works for Hung Hing
Road Diversion Stage.
·
Installation
of precast concrete short pipe extended from the existing 1800 drainage at Box
Culvert N landside.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Excavation
and Lateral Support works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Bored
piling at eastern breakwater
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f drainage pipe
·
Construction
of Pile cap & column (Land)
·
Dismantling
of marine platform
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
Noise Monitoring
Air Monitoring
CMA2a: from 13 December 2012 to 14 December 2012
CMA3a: from 22 December 2012 to 24 December 2012
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no.
HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works under FEP-03/364/2009
·
No
further work under designated project1
1Remarks: The construction of bored pile E3B under
FEP-03/364/2009 was confirmed completed and the bored pile E3B and the works
area was handover to contract
no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Cooling
main bridge construction
·
Pre-bored
H-piling
·
Bridge
construction
·
Cooling
main bridge construction
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
·
Removal
of remaining guide wall along
·
Installation
of pre-bored H-pile in CWB stage 2 (from Ch120 to Ch220)
·
Backfilling
works at SCL section
·
Plant
mobilization for CWB diaphragm wall construction work
·
Pre-treatment
works and guide wall construction for CWB Diaphragm Wall
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Trimming
of bored pile head and blinding for the base slab construction at tunnel
portion 1.
·
Waterproofing
installation for the base slab at tunnel portion 1.
·
Rebar
fixing and base slab concreting at Tunnel Portion 1.
·
G.I.
and remove the temporary sheetpile wall at WCR2
·
Diaphragm
wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
·
Bulkhead
at Bay 14 of Box Culvert “O” and stage 2 diversion of uncharted drainage works
at Box culvert “O”.
·
Trial
excavation, footpath set back, UU diversion, tree transplantation, reprovision
of street furniture and preparation works for Hung Hing Road Diversion Stage 1.
·
Caisson
seawall precast unit 2X in-situ work on flat-top barge.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
ELS
works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
·
Construction
of Diaphragm Wall at TS2
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f drainage pipe
·
Construction
of Pile caps & columns (Land)
·
Dismantling
of marine platform
·
Demolition
of parapet at IEC Link
·
Construction
of Pile caps & columns (Marine)
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009/B and Further Environmental permit
nos. FEP-01/364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A
to implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the
approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor
Link (Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the
Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification
Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/B,
Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009,
FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and
FEP-08/364/2009/A during the period Sep to Oct 2012. The cut-off date of reporting is at 27th of
each reporting month
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designated
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane
trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in
length defined from the connection with the existing Rumsey Street Flyover in
Central, through to a connection with the existing Island Eastern Corridor to
the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central
Interchange near the Rumsey Street Flyover to provide road connections to the
Central area;
·
Tunnel control
buildings and ventilation buildings;
·
Slip roads to
connect the CWB to the local road system in the Wan Chai North and
·
Associated road
lighting, road signing, traffic control and surveillance system; and
·
Other associated
works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs)
to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these
Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual
Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key personnel and contact particulars
are summarized in Table 2.3:
Table 2.3 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566 7522 |
Contractor’s Representative |
Mr. Chung Man Shek |
2566 4866 |
|||
Site Agent |
Mr. Tong Au |
9725 5874 |
|||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
|||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
|||
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 2467 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Calvin Leung |
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
|
Deputy Site Agent |
Mr. Roger Wong |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214 7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
2214 7742 |
|||
Environmental Supervisor |
K. W. Lee |
6461 4623 |
|||
|
|
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|
|
|
Environmental Supervisor |
Bosco Lee |
2214 7711 |
|
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
Mr. P.J. Fan |
3557 6368 |
2566 2192 |
||
Contractor’s
Representative |
Mr. David Lau |
3557 6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr. Clement
Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/17 – Central
– Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
·
No
further work under designated project1
1Remarks:
The construction of bored pile E3B under FEP-03/364/2009 was confirmed
completed and the bored pile E3B and the works area was handover to contract no. HY/2009/19 on 30
November 2012.
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Pre-bored
H-piling
·
Bridge
construction
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at
·
Backfilling
works on top of SCL protection works.
·
Jet
grouting to HKCEC new extension foundation.
·
Plant
mobilization for installation of pre-bored H-pile works at Stage 1b & Stage
2
·
Pre-drilling
works for CWB (Stage 2).
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Trimming
of pile head and blinding laying construction at WCR1 of Tunnel Portion 1
·
Waterproofing
installation at WCR1 of Tunnel Portion 1 Bay 2 - Bay 7 together with Bay 8 – Bay
16
·
Preparation
works for extract the western temporary sheetpile wall
·
Diaphragm
wall of panel P106, C107, P108, C109, P110, C111, P112, P114, C115 & P116.
Panel P113.
·
Preparation
works of saw cut Southern Diaphragm wall for the connection between existing
drainage and Bay 1 of Box Culvert N1.
·
Trial
excavation, Footpath Set back, UU Diversion and preparation works for Hung Hing
Road Diversion Stage.
·
Installation
of precast concrete short pipe extended from the existing 1800 drainage at Box
Culvert N landside.
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (
·
Excavation
and Lateral Support works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Bored
piling at eastern breakwater
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f
drainage pipe
·
Construction
of Pile cap & column (Land)
·
Dismantling
of marine platform
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
2.4.4.
In coming
reporting month, the principal work activities of
individual contracts are anticipated as follows:
Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
·
No
further work under designated project1
1Remarks: The construction of bored pile E3B under
FEP-03/364/2009 was confirmed completed and the bored pile E3B and the works
area was handover to contract
no. HY/2009/19 on 30 November 2012.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Excavation
of trial pit
·
Transplanting
of trees
·
Hoarding
erection and modification
·
Installation
of couplers, UU detection, trial trench, pre-drilling
·
Excavation
·
Sheet
Piling
·
Drainage
works
·
Tunnel
works
·
Trough
structure construction and associated drilling and grouting
·
Road
works
·
OHVD
installation
·
Pipe-piling
works
·
Cooling
main bridge construction
·
Pre-bored
H-piling
·
Bridge
construction
·
Cooling
main bridge construction
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
·
Removal
of remaining guide wall along
·
Installation
of pre-bored H-pile in CWB stage 2 (from Ch120 to Ch220)
·
Backfilling
works at SCL section
·
Plant
mobilization for CWB diaphragm wall construction work
·
Pre-treatment
works and guide wall construction for CWB Diaphragm Wall
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Trimming
of bored pile head and blinding for the base slab construction at tunnel
portion 1.
·
Waterproofing
installation for the base slab at tunnel portion 1.
·
Rebar
fixing and base slab concreting at Tunnel Portion 1.
·
G.I.
and remove the temporary sheetpile wall at WCR2
·
Diaphragm
wall construction for Eastern Bulkhead Panel BHP3 and BHP7.
·
Bulkhead
at Bay 14 of Box Culvert “O” and stage 2 diversion of uncharted drainage works
at Box culvert “O”.
·
Trial
excavation, footpath set back, UU diversion, tree transplantation, reprovision
of street furniture and preparation works for Hung Hing Road Diversion Stage 1.
·
Caisson
seawall precast unit 2X in-situ work on flat-top barge.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
ELS
works at TS4
·
Rock
breaking works at TPCWAE
·
Tunnel
works at TS1
·
Horizontal
drilling for mined tunnel
·
Pipe
roofing installation
·
Construction
of Diaphragm Wall at TS2
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
·
Road
works at
·
Bored
piling (Land)
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall
Construction (North & South Section)
·
Guide
wall construction for D-wall / Barrette at North side
·
Construction
works for Box Culvert T1
·
Marine
Piling
·
Construct
ion of socket-H pile
·
Construction
works for Culvert U1
·
Construction
of 1500f drainage pipe
·
Construction
of Pile caps & columns (Land)
·
Dismantling
of marine platform
·
Demolition
of parapet at IEC Link
·
Construction
of Pile caps & columns (Marine)
·
Cut
& Cover Tunnel sheet piling works
·
Construction
of dewatering well for Cut & Cover Tunnel
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
·
Construction
of Pre-cast Unit in
3.1.1.
A
summary of the current status on licences and/or permits on environmental
protection pertinent to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Superseded |
Environmental
Permit |
EP-364/2009/B |
20 Sep
2012 |
Valid |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
24 Mar
2010 |
Valid |
|
Further
Environmental Permit |
21 Apr 2010 |
Valid |
|
Further
Environmental Permit |
12 July 2010 |
Valid |
|
Further
Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further
Environmental Permit |
15 Nov 2010 |
Valid |
|
Further
Environmental Permit |
22 Nov 2010 |
Valid |
|
Further
Environmental Permit |
25 Feb 2011 |
Valid |
|
Further
Environmental Permit |
15 June 2012 |
Valid |
3.1.2.
Due
to the multi-contract nature of the Project, the status of permits and/or
licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and
submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.
Table 3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account
under Waste Disposal Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4.
The construction works was completed,
and the FEP was surrendered by the Contractor on 11 February 2011.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and
submission under FEP-02/364/2009 for contract no.
HK/2009/01
are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-pilling equipment |
GW-RS-1293-12 |
10 Dec 2012 |
10 Dec 2012 to 9 June 2013 |
Valid |
GW-RS0760-12 |
16 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03 Feb 2013 |
Cancelled |
|
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Cancelled |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01 Feb 2013 |
Cancelled |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2013 |
Cancelled |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb 2013 |
Cancelled |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15 Mar 2013 |
Cancelled |
|
GW-RS0994-12 |
25 Sep 2012 |
25 Sep 2012 to 19 Nov 2012 |
Expired |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Cancelled |
|
GW-RS1017-12 |
27 Sep 2012 |
30 Sep 2012 to 24 Mar 2013 |
Valid |
|
GW-RS0793-12 |
21 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Valid |
|
GW-RS1040-12 |
8 Oct 2012 |
13 Oct 2012 to 12
Apr 2013 |
Valid |
|
GW-RS1177-12 |
15 Nov 2012 |
17 Nov 2012 to10
May 2013 |
Valid |
|
GW-RS1184 -12 |
15 Nov 2012 |
17 Nov 2012 to 8
May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov 2012 |
21 Nov 2012 to 8
May 2013 |
Valid |
|
GW-RS1179-12 |
20 Nov 2012 |
22 Nov 2012 to 21
May 2013 |
Valid |
|
GW-RS1187-12 |
20 Nov 2012 |
27 Nov 2012 to 26
May 2013 |
Valid |
|
GW-RS1199-12 |
20 Nov 2012 |
26 Nov 2012 to 25
May 2013 |
Valid |
|
Discharge Licence |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
WT00006220-2010 |
18 Mar 2010 |
31
Mar 2015 |
Valid |
|
Billing
account under Waste Disposal Ordinance |
7010069 |
21
Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.5 Summary
of submission
status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
20 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
3.1.6.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-01/364/2009 for
contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of
Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr 2013 |
Valid |
GW-RS1069-12 |
17 Oct 2012 |
19 Oct 2012 to 18 Apr 2013 |
Valid |
|
GW-RS1076-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1204-12 |
9 Nov 2012 |
29 Nov 2012 to 23 May 2013 |
Valid |
|
GW-RS1272-12 |
5 Dec 2012 |
5 Dec 2012 to 26 May 2013 |
Valid |
|
GW-RS1223-12 |
27 Nov 2012 |
7 Dec 2012 to 5 June 2013 |
Valid |
|
GW-RS1243-12 |
3 Dec 2012 |
5 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RE1055-12 |
30 Nov 2012 |
3 Dec 2012 to 29 May 2013 |
Valid |
|
GW-RS1228-12 |
30 Nov 2012 |
30 Nov 2012 to 29 May 2013 |
Valid |
|
GW-RS1245-12 |
5 Dec 2012 |
6 Dec 2012 to 5 May 2013 |
Valid |
|
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Expired |
|
GW-RS0611-12 |
14 Jun 2012 |
15 Jun 2012 to 28 Nov 2012 |
Expired |
|
GW-RS0633-12 |
13 Jun 2012 |
16 Jun 2012 to 14 Dec 2012 |
Expired |
|
GW-RS0671-12 |
25 Jun 2012 |
17 Jul 2012 to 16 Jan 2013 |
Valid |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan
2013 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS0814-12 |
3 Aug 2012 |
6 Aug 2012 to 5 Dec 2012 |
Expired |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
|
GW-RS0996-12 |
25 Sept 2012 |
26 Sept 2012 to 25 Mar 2013 |
Valid |
|
GW-RS1084-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
|
GW-RS1086-12 |
25 Oct 2012 |
28 Oct 2012 to 16 Apr 2013 |
Valid |
|
GW-RS1174-12 |
9 Nov 2012 |
11 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1158-12 |
16 Nov 2012 |
18 Nov 2012 to 16 May 2013 |
Valid |
|
GW-RS1167-12 |
16 Nov 2012 |
23 Nov 2012 to 21 May 2013 |
Valid |
|
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of Submission |
Condition 2.7 and 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Condition 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Condition 2.11 |
Landscape Plan
(Revision B) |
20 Nov 2012 |
Condition 2.9 |
Noise Management Plan
(Revision A) |
13 Jan 2012 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary
of the current status on licences and/or permits on environmental protection
pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS0769-12 |
23 Jul 2012 |
25 Jul 2012 – |
Valid |
GW-RS0833-12 |
09 Aug 2012 |
09 Aug 2012 – |
Valid |
|
GW-RS0925-12 |
31 Aug 2012 |
3 Sep 2012 – |
Cancelled |
|
GW-RS1208-12 |
23 Nov 2012 |
26 Nov 2012- 31 Mar 2013 |
Valid |
|
GW-RS1286-12 |
07 Dec 2012 |
11 Dec 2012- 05 Jun 2013 |
Valid |
|
Discharge Licence |
WT00012998-2012 |
25 May 2012 |
31 Jan 2016 |
Valid |
WT00012967-2012 |
17 Sep 2012 |
30 Sep 2017 |
Valid |
|
Registration as a Waste Producer |
WPN:
8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration
completed |
Billing Account
under Waste Disposal Ordinance (Land) |
Account No.:
7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9 Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management
Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan
(Rev. 5) |
12 March 2012 |
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
3.1.8.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for
contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for bored pile
construction at Eastern Breakwater of CBTS |
GW-RS1009-12 |
03 Oct 2012 |
03 Oct 2012 to 25 Mar 2013 |
Valid |
Construction
Noise Permit (CNP) for non-piling
equipment |
GW-RS1153-12 |
15 Nov 2012 |
15 Nov 2012 to 06 May 2013 |
Valid |
GW-RS1191-12 |
26 Nov 2012 |
26 Nov 2012 to 11 May 2013 |
Valid |
|
GW-RS1044-12 |
09 Oct 2012 |
10 Oct 2012 to 30 Nov 2012 |
Expired |
|
GW-RS0695-12 |
24 Jun
2011 |
25 Jun
2012 to 21 Dec
2012 |
Expired |
|
GW-RS0700-12 |
26 Jun
2012 |
26 Jun
2012 to 25 Dec
2012 |
Expired |
|
GW-RS0607-12 |
12 Jun
2012 |
13 Jun
2012 to 7 Dec
2012 |
Expired |
|
GW-RS0789-12 |
27 Jul
2012 |
1 Aug
2012 to 25 Jan
2013 |
Valid |
|
GW-RS0924-12 |
31 Aug
2012 |
01 Sep
2012 to 28 Feb
2013 |
Valid |
|
GW-RS0984-12 |
21 Sep
2012 |
23 Sep
2012 to 22 Mar
2013 |
Valid |
|
GW-RS1345-12 |
21 Dec 12 |
24 Dec 12 to 23 Jun 2013 |
Valid |
|
|
GW-RS1342-12 |
21 Dec 2012 |
26 Dec 2012 to 25 Jun 2013 |
Valid |
Registration
as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010
to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance
(Dumping by Vessel) |
7011761 |
10 Jul 2012 |
17 Oct 2012 to 16 Jan 2012 |
Valid |
Water Discharge License (Discharge at |
WT00008780-2011 |
24 Nov 2011 |
24 Nov 2011 to 31 Mar 2016 |
Valid |
Water Discharge License (Discharge at CHT area) |
WT00012941-2012 |
10 May 2012 |
10 May 2012 to 31 May 2014 |
Valid |
Water Discharge License (Discharge at TPCWAE) |
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011 to 31 Dec 2013 |
Valid |
Water Discharge License (Discharge at TS4) |
WT00011718-2012 |
16 Jan 2012 |
16 Jan 2012 to 31 Jan 2014 |
Valid |
Table 3.11 Summary
of submission status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works Schedule |
15 Mar
2011 |
Condition
2.8 |
Location Plan |
15 Mar
2011 |
Condition
2.23 |
Noise
Management Plan |
6 May
2011 |
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status on licences and/or permits on
environmental protection pertinent and submission under
FEP-07/364/2009/A for
contract no. HY/2009/19 are shown in Table 3.12 and Table
3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction
Noise Permit (CNP) |
GW-RS1230-12 |
28 Nov 2012 |
28 Nov 12 to 25 May 13 |
Valid |
GW-RS0589-12 |
18-Jun-12 |
17-Dec-12 |
Cancelled |
|
GW-RS1065-12 |
16-Oct-12 |
20-Oct-12 to 20-Apr-13 |
Valid |
|
GW-RS0871-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
|
GW-RS0885-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
|
GW-RS0953-12 |
17-Sep-12 |
21-Sep-12 to 20-Mar-13 |
Cancelled |
|
GW-RS1210-12 |
29-Nov-12 |
29 Nov 12 to 28 May 13 |
Valid |
|
Water Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Cancelled |
|
WT00010093-2011 |
17-Aug-12 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table 3.13 Summary of
submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date
of Submission |
Condition 2.9 |
Noise Management Plan |
02 Jun 2011 |
Condition 2.13 |
Landscape Plan |
16 March
2012 |
Condition 2.9 |
Noise Management Plan(Rev.2) |
28
October 2011 |
Contract no.
HK/2010/06 - Wan Chai Development Phase II – Central –Wanchai Bypass over
MTR
Tsuen Wan Line
3.1.10.
The current status on licences and/or
permits on environmental protection pertinent and
submission under FEP-08/364/2009/A for contract no. HK/2010/06 showed in Table 3.14 and Table 3.15.
Table 3.14 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-08/364/2009/A |
15 June 2012 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS0923-12 |
31 Aug 2012 |
15 Oct 2012 – 14 Apr 2013 |
Valid |
Table 3.15 Summary of
submission status under FEP-08/364/2009
EP Condition |
Submission |
Date of Submission |
|
Acknowledgement
letter of FEP-08/364/2009A |
14 Aug 2012 |
Condition 2.9 |
Noise Management
Plan |
26 Nov 2012 |
Noise Monitoring Stations
4.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit
Levels for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
*M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
*M8 |
City
Hall |
*
Remark 1: Location ID has been updated from M7 to M8 for City Hall
*
Remark 2: M7e has become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
4.1.2.
Review of feasibility on the real time noise
monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan
fireboat Station was found not appropriate to be a monitoring station for
monitoring the IECL Piling works and Demolition after visited.
4.1.3.
The
noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2 Real Time Noise Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitfield Depot |
North Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu |
Noise Monitoring
Parameters, Frequency and Duration
4.1.4.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure
level (Leq). Leq (30 minutes) shall be used as the
monitoring parameter for the time period between 0700
and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
4.1.5.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
One set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.6.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
·
One set of
measurements between 0700 and 1900 hours on normal weekdays.
·
One set of
measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300
hours on public holidays.
·
One set of
measurements between 2300 and 0700 hours on next day on everyday.
4.1.7.
If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.8.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring. Immediately
prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency. Measurements may be accepted as valid only
if the calibration level from before and after the noise measurement agree to
within 1.0 dB.
4.1.9.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
4.1.10. The sound
level meter shall be checked using an acoustic calibrator generating a known
sound pressure level at a known frequency before deployment to the site and
during each site visit. Measurements will be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community Liaison
Centre |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
Remarks: As per
the ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB site
office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity controlled
chamber followed by accurate weighing by an electronic balance with readout
down to 0.1 mg. The balance shall be regularly calibrated against a traceable
standard.
4.2.10.
All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11.
Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designated project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (
Contract no. HY/2009/17 – Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under
FEP-07/364/2009
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central - Wan Chai Bypass at Wan Chai East
Contract no. HK/2010/06 - Wan Chai Development
Phase II – Central - Wan Chai Bypass over MTR Tsuen Wan Line
5.0.3.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix
5.1.
5.1.1.
Monitoring for report of review baseline noise
level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation of this reporting month starting from January 2012.
Contract no. HY/2009/17 –Central – Wan
Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
5.1.2.
The proposed division of noise monitoring stations
for Contract no. HY/2009/17 are summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
5.1.3.
No action or limit level exceedance was recorded
during daytime period in the reporting month. Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.4.
Noise monitoring for the Central Interchange works
under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed
division of noise monitoring stations for Contract no. HY/2009/18 are
summarized in Table 5.2 below:
Table 5.2 Noise
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has
become a reference station starting from 7 Aug 2012
5.1.5.
One limit level exceedance was recorded at M8- City
Hall on 27 Dec 2012 in the reporting month.
5.1.6.
Tourist gathering at City Hall and no major
construction activities were observed during monitoring. As such, the limit level
exceedance was considered as non project related.
5.1.7.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre – Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 – Wan
Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
5.1.8.
The commencement of construction works for Contract
no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under
FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring
stations are summarized in Table 5.3 below.
Table 5.3 Noise Monitoring Station for Contract
no HK/2009/01
and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.9.
No
action or limit level exceedance was recorded in the reporting month. Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix
5.2.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (
5.1.10. The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.4 below.
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.11.
No action or limit level exceedance was recorded in
this reporting month.
5.1.12.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2.
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
5.1.13. Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table
5.5 below.
Table 5.5 Noise Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
5.1.14.
Four
limit level exceedances were
recorded on 29 November, 11 December 2012, 17 December 2012 and 27 December
2012 at M6 – HK Baptist Church
Henrietta Secondary School in the reporting month.
5.1.15.
Major traffic noise observed during monitoring was
considered as the major noise contribution. As such, the limit level exceedances
were concluded as non-project related.
5.1.16.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
5.2.1.
As
confirmed by CWB RSS, the IECL parapet removal operations will commence in
October 2012. Liaison was conducted
with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo
Fan Memorial School regarding the set up of RTN3 real time noise monitoring
station.
5.2.2.
Po
Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep
2012 and station set up was performed on 14 Sep 2012. Real time noise baseline
capturing was conducted during time period without construction work from 21
Sep 2012 to 04 Oct 2012.
5.2.3.
Real time noise monitoring
at RTN3 - Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct
2012.
5.2.4.
Oil
Street Community Liaison Centre was confirmed to be demolished in mid-October
by CWB RSS. This presented a need
for relocation of RTN2 – Oil Street Community Liaison Centre. After liaison with Hong Kong Electric,
permission was granted on 21 Sep 2012 for real time noise monitoring set up at
City Garden Electric Centre (RTN2a – Electric Centre), which is a
representative of the noise sensitive receiver City Garden.
5.2.5.
RTN2
previously located at oil Street Community Liaison Centre was relocated to Hong
Kong Electric Centre on 5 Oct 2012, which is a representative of the noise
sensitive
5.2.6.
No construction activity was conducted during night
time period (2300 to 0700) in this reporting month.
Contract no. HY/2009/17 –Central – Wan Chai Bypass
(CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009 and
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under FEP-07/364/2009/A
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
Real time noise monitoring
results and graphical presentation during night time period are for information
only.
5.2.8.
No action or limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.
5.2.9.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix 5.4 .
5.2.10.
The proposed division of noise monitoring stations
are summarized in Table 5.7 below. Real time noise monitoring for
major construction works under contract no. HY/2009/19 was commenced on 24
April 2011.
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North Point |
Electric Centre |
RTN3 |
North Point |
Po Leung Kuk Yu |
* Real time noise monitoring results and graphical
presentation during night time period are for information only.
** Real time
noise monitoring results and graphical presentation of RTN3 are for reference
as the demolition work at the IECL has not commenced.
5.2.11.
No action or limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.
5.2.12.
A limit level exceedance was recorded at
RTN2a-Electric Centre on 7 Dec 2012 in the reporting month. After checking with
contractor, no major noisy construction works were conducted during the time
period and the non CWB project construction activities near Electric Centre was
considered to be the major source of noise impact. As such, the exceedance was
concluded as non-project related.
5.2.13.
Real time noise monitoring results measured in this
reporting period are reviewed and summarized. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.4.
5.3.1
Due to extension of site boundary by contractor of
HY/2009/19, location of air monitoring station CMA1b – Oil Street Community
Liaison Centre has been finely adjusted on 21 April 2012.
5.3.2
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled:
CMA2a: from 13 December 2012 to 14 December
2012
CMA3a: from 22 December 2012 to 24 December
2012.
Contract
no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot –
Advanced piling works under FEP-03/364/2009
5.3.3
The proposed division of air monitoring stations
are summarized in Table 5.8 below. Air monitoring for the piling
works under contract no. HY/2009/17 was commenced on 8 October 2010.
Table 5.8 Air Monitoring Station for Contract
no. HY/2009/17
Station |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
CMA2a |
|
5.3.4
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix
5.3.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.5
Air monitoring for the Central Interchange works
under contract no. HY/2009/18 was commenced on 21 April 2011. The proposed
division of air monitoring stations are summarized in Table 5.9
below.
Table 5.9 Air Monitoring Stations for Contract
no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
5.3.6
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix
5.3.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at
5.3.7
The commencement of construction works for Contract
no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air
monitoring stations are summarized in Table 5.10 below.
Table 5.10 Air Monitoring Station for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
5.3.8
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix
5.3.
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
5.3.9
The commencement of construction works for HK/2009/02
under FEP-01/364/2009 is on 26 April 2011. The proposed division of air
monitoring stations are summarized in Table 5.11 below.
Table 5.11 Air Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.10
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix
5.3.
Contract no.
HY/2009/15 – Central-Wanchai Bypass – Tunnel (
5.3.11 The
commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A
was on 13 July 2011. Air quality monitoring was commenced on 14 July 2011.
The proposed division of air monitoring stations are summarized in Table
5.12
below.
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.12
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix
5.3.
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
5.3.13
The proposed division of air monitoring stations
are summarized in Table 5.13 below. Air monitoring for the tunnel
works under contract no. HY/2009/19 was commenced on 26 April 2011.
Table 5.13 Air Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
5.3.14
No exceedance was recorded in the reporting month.
Air quality monitoring results measured in this reporting period are reviewed
and summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix
5.3.
Contract no. HY/2009/17 –Central
– Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
5.4.1.
No Inert and non-inert C&D wastes were disposed
in the reporting month. Details of the waste flow table are summarized in Table
5.14
Table 5.14 Details of Waste Disposal
for Contract no. HY/2009/17
Waste Type |
Quantity this month, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIl |
Nil |
CWBP / TKO137 |
Inert C&D materials recycled |
Nil |
1354.82 |
SENT |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
5.4.2.
No Inert
C&D wastes were recycled and non-inert C&D wastes were disposed of in
this reporting month. Details of the waste flow table are summarized in Table 5.15.
Table 5.15 Details
of Waste Disposal for Contract no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed |
Nil |
22249.345 |
TKO137, TM38 |
Inert C&D materials recycled |
Nil |
5104.5 |
N/A |
Non-inert C&D materials disposed |
65.48 |
1116.08 |
SENT Landfill |
Non-inert C&D materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
300 |
8650 |
N/A |
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.3.
Inert C&D & non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.16.
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
5882.35 |
225299.38 |
TKO137 / TM 38 |
N/A |
Inert C&D materials recycled, m3 |
0 |
18161 |
n/a |
N/A |
Non-inert C&D materials disposed, m3 |
48.54 |
745.91 |
SENT Landfill |
N/A |
Non-inert C&D materials recycled, m3 |
N/A |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
6221 |
SENT Landfill |
N/A |
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.4.4.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HY/2009/18
70956 |
|||
38887 |
|||
794 |
|||
73.21 |
|||
3565 |
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
5.4.5.
Inert
& Non-inert C&D wastes were disposed of in this reporting month. Details
of the waste flow table are summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month(m3) |
Cumulative Quantity-to-Date(m3) |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
3088 159.4 |
186454.9 150593.7 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials recycled, m3 |
120160.3 |
203354.6 |
HY/2009/11 ex-PCWA TS4 TS2 |
Non-inert C&D materials disposed, m3 |
25.4 |
587.1 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
59.5 |
542651 kg |
Xun Xiang Metalware Skylight Recycle (paper) |
Chemical waste disposed, kg |
15 |
12,051 |
Dunwell Group |
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.6.
Inert and Non-inert C&D wastes were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/19
Inert C&D
materials disposed |
N/A |
||
Inert C&D
materials recycled |
N/A |
||
Non-inert C&D
materials disposed |
SENT Landfill |
||
Non-inert C&D
materials recycled |
N/A |
||
Chemical waste disposed |
N/A |
Contract no. HK/2010/06 Wan
Chai Development Phase II - Central-Wan Chai Bypass over MTR Tsuen Wan Line
under FEP-08/364/2009/A
5.4.7.
No inert and Non-inert C&D wastes were disposed
of in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
6.0.1.
The Event Action Plan for construction noise, air
qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot –
Advanced piling works under FEP-03/364/2009
6.1.1.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.1.2.
One limit level exceedance was recorded on 27 Dec
2012 at M8- City Hall in the reporting month. Investigation found that noise
from tourist gathering was contributed in the noise monitoring an exceedance
was not related to the project.
Contract no. HK/2009/01 – Wan Chai Development Phase II
– Central – Wan Chai Bypass at
6.1.3.
No exceedance was recorded in the reporting month.
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.4.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
6.1.5.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
6.1.6.
Four
limit level
exceedances were recorded on 29 November, 11 December 2012, 17 December 2012 and
27 December 2012 at M6 – HK Baptist
Church Henrietta Secondary School in the reporting month. Investigations found that major traffic
noise was contributed in the noise monitoring and exceedances were not
related to the Project.
Real Time Noise Monitoring
Contract no.
HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works under FEP-03/364/2009
6.1.7.
No action or limit level exceedance was recorded in
the reporting month.
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
6.2.1.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
6.2.2.
No exceedance was recorded in the reporting month.
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
6.2.3.
No exceedance was recorded in the reporting month.
Contract no. HK/2009/02 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
6.2.4.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
6.2.5.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceedance was recorded in the reporting month.
6.3.1.
There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.3.2.
No project-related non-compliance from monitoring
was recorded in the reporting month.
7.0.1.
According to Condition 3.4 of the EP-364/2009/B,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According to the Monthly EM&A report (November
2012) of Central Reclamation Phase III (CRIII), filling works, road works, building
construction works and pipe works were performed in the November 2012 reporting
month. The water quality monitoring was completed in October 2011 and no Project-related
exceedance was recorded for air and noise monitoring. It can be concluded that cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activity under Wan Chai Development Phase II
was marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains,
Cooling Watermains and Salt Watermains Installations, tunnel works at Wan Chai
East, ELS work at TS4 and deep excavation at TPCWAE
TCBR1W. Excavation of trial pit at Central Interchange, and marine pilling and
box culvert construction at North Point area. The major environmental impact
was water quality impact at
7.0.4.
The major environmental impacts generated from excavation
at Central and tunnel works at Wan Chai East, IECL and Causeway Bay Typhoon Shelter
were undertaken in the reporting month. No significant air impact was
anticipated in the reporting month. Besides, no project-related exceedances were
recorded during the environmental monitoring events in the reporting
month. Thus, it is evaluated that
the cumulative construction impact from the concurrent projects including Wan
Chai Development Phase II was insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HY/2009/15, HY/2009/17,
HY/2009/18, HY/2009/19, HK/2009/01, HK/2009/02 and HK/2010/06. No
non-conformance was identified during the site audits.
8.0.2.
Four site inspections for Contract no. HY/2009/15
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Date |
Item |
Observations |
Action taken by Contractor |
Outcome |
121204_01 |
4-Dec-12 |
Filling materials should be avoid resting at the edge of seawall
block to prevent overflow(TS2) |
Filling material was removed from the edge of seawall block. |
Completion as observed on 11 Dec 2012. |
121204_02 |
4-Dec-12 |
Drip trays should be provided for oil drums(TS4,TS2) |
Drip trays were provided for oil drums. |
Completion as observed on 11 Dec 2012. |
121204_03 |
4-Dec-12 |
Milky discharge observed at treatment outfall(Ex-PCWA) |
Chemical dosage was readjusted and milky discharge ceased. |
Completion as observed on 11 Dec 2012. |
121211_03 |
11-Dec-12 |
Drip tray should be provided for oil drum (TS1 near landing step) |
Tarpaulin covering was provided
to prevent leakage from oil drum |
Completion as observed on 18 Dec 2012. |
121211_04 |
11-Dec-12 |
Silt Curtain should be provided to barges carrying out filling material loading |
Silt curtain was provided around loading barges. |
Completion as observed on 18 Dec 2012. |
121211_05 |
11-Dec-12 |
Sump trap should be cleared to prevent overflow (TS1breakwater) |
Sump trap was cleared |
Completion as observed on 18 Dec 2012. |
121218_04 |
18-Dec-12 |
Drip tray should be provided for oil bucket (TS2, SI work area) |
Drip trays were provided |
Completion as observed on 27 Dec 2012. |
121227_01 |
27-Dec-12 |
Water pumping line should be connected to proper collection point
or water treatment facilities (TS2) |
Water pumping line was properly connected. |
Completion as observed on 03 Jan 2013. |
121227_02 |
27-Dec-12 |
Defects were observed at southern seawall block at TS2.
Contractor was advised to deploy
impermeable barrier properly around the concerned seawall block during
rectification work |
Silt curtain and impermeable barrier
are properly deployed. |
Completion as observed on 08 Jan 2013. |
121227_03 |
27-Dec-12 |
The condition of the tarpaulin provided to filling material
loading barge should be improved to avoid holes. |
The condition of the tarpaulin was improved |
Completion as observed on 03 Jan 2013. |
8.0.3.
Five site inspections for Contract no. HY/2009/18
was carried out during this reporting period. No observation is found in the reporting month.
8.0.4.
Four site inspections for Contract no. HY/2009/19
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.2
Table 8.2 Summary of Environmental
Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
121129_01 |
29-Nov-12 |
Muddy water discharge observed at outfall location |
Muddy discharge terminated and protection work was provided to outfall. |
Completion as observed on 05 Dec 2012. |
8.0.5.
Four site inspections for Contract no. HK/2009/01
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.3
Table 8.3 Summary of Environmental
Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
121128_01 |
28-Nov-12 |
The mud trail was observed on the public road which should be
cleaned. The measures should be taken to avoid the mud from vehivle or trucks
deposited on road. (Near to Grand Hyatt) |
The mud trail was cleaned. |
Completion as observed on 12-Dec-12 |
121128_02 |
28-Nov-12 |
The oil drum should be provided with drip tray. (VIP area) |
Drip tray was provided for oil drum. |
Completion as observed on 12-Dec-12 |
121220_01 |
20-Dec-12 |
The stockpile should be covered by tarpaulin sheet ( |
The stockpile was covered by tarpaulin sheet |
Completion as observed on 27-Dec-12 |
121220_02 |
20-Dec-12 |
The oil stain was observed on ground which should be cleaned and
removed as chemical waste. (VIP area, Near to Grand Hyatt) |
The oil stain was removed |
Completion as observed on 27-Dec-12 |
121220_03 |
20-Dec-12 |
The dusty trail was observed on the public road which should be
cleaned up (VIP area) |
The dustry trail was cleaned. |
Completion as observed on 27-Dec-12 |
121227_01 |
27-Dec-12 |
Drip tray should be provided for oil drums (Water Channel) |
Drip tray was provided for oil drum. |
Completion as observed on 2-Jan-13 |
8.0.6.
Four site inspections for Contract no. HK/2009/02
was carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.4
Table 8.4 Summary of Environmental
Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
121206_01 |
6-Dec-12 |
The
condition of silt curtain should be improved to prevent any gaps to occur
(Eastern Temporary seawall) |
The
condition of silt curtain has been improved. |
Completion
as observed on 13-Dec-12 |
121206_02 |
6-Dec-12 |
The label
should be provided for chemical waste container (WCR1) |
The label
was provided for chemical waste container. |
Completion
as observed on 13-Dec-12 |
121218_01 |
18-Dec-12 |
The
condition of silt curtain for the Eastern temporary seawall should be
improved and prevent the occurrence of gaps. (Eastern Temporary seawall) |
The
condition of silt curtain has been improved. |
Completion
as observed on 27-Dec-12 |
121227_01 |
27-Dec-12 |
Watering
within site area should be provided more regularly (WCR1) |
Water
spraying with site area was observed. |
Completion
as observed on 3-Jan-12 |
121227_02 |
27-Dec-12 |
The oil
stain was observed on ground which should be cleaned and removed as chemical
waster (WCR1) |
The oil
stain was removed. |
Completion
as observed on 3-Jan-12 |
8.0.7.
Three site inspections for Contract no. HY/2009/17
were carried out during this reporting period1. No observation
was found in the reporting month.
Remarks1:
Construction of bored pile E3B under HY/2009/17 was confirmed completed and the
respective work area under FEP was inspected under HY/2009/19 from 19 Dec 2012
onwards.
8.0.8.
Four site
inspections for Contract no. HK/2010/06 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.5
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by
Contractor |
Outcome |
121203_01 |
3-Dec-12 |
The oil leakage from the hole of drip tray was observed which
should be removed and the drip tray should be reparied (2e) |
The oil stain was removed and the drip tray was repaired. |
Completion as observed on 10-Dec-12 |
121220_01 |
20-Dec-12 |
The oil stain was observed on the platform which should be
cleaned and removed as chemical waste |
The oil stain was removed. |
Completion as observed on 24-Dec-12 |
121220_02 |
20-Dec-12 |
Drip tray should be provided for oil drum (Barge) |
The oil drum was removed. |
Completion as observed on 31-Dec-12 |
121224_01 |
24-Dec-12 |
The stockpile should be covered by tarpaulin sheet. (section 2) |
The stockpile was removed. |
Completion as observed on 31-Dec-12 |
121224_02 |
24-Dec-12 |
Watering within site area should be provided more regularly. (2w,
Section 2) |
Water spraying within the site area was observed. |
Completion as observed on 31-Dec-12 |
9.0.1.
No environmental complaint was received in the
reporting period.
9.0.2.
The
details of cumulative complaint log and updated summary of complaints are
presented in Appendix 9.1
9.0.3.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Dec12 |
0 |
Sep10 - Nov12 |
20 |
Total |
20 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1. The construction
programmes of individual contracts are provided in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
Contract
No. |
Key Construction Works |
Recommended
Mitigation Measures |
HY/2009/15 |
·
ELS
works at TS4 ·
Rock
breaking works at TPCWAE ·
Tunnel
works at TS1 ·
Horizontal
drilling for mined tunnel ·
Pipe
roofing installation ·
Construction
of Diaphragm Wall at TS2 |
·
Watering
any dust generating activities ·
Checking
all drip trays frequently and clear any stagnant water and mud inside it. Noise control
measures shall be provided during restricted hours |
HY/2009/17 |
·
No
further works under designated project |
·
N/A |
HY/2009/18 |
·
Excavation
of trial pit ·
Transplanting
of trees ·
Hoarding
erection and modification ·
Installation
of couplers, UU detection, trial trench, pre-drilling ·
Excavation ·
Sheet
Piling ·
Drainage
works ·
Tunnel
works ·
Trough
structure construction and associated drilling and grouting ·
Road
works ·
OHVD
installation ·
Pipe-piling
works ·
Cooling
main bridge construction ·
Pre-bored
H-piling ·
Bridge
construction |
·
Noise
barrier shall be implemented; and ·
Noise
level shall be controlled by reducing piling rate and no. of plants working
in parallel. ·
Dust
control during dust generating activities ·
Provide
protection works to ensure no runoff out of site area or direct discharge
into public drainage system. ·
Appropriate
plants and measures should be taken to ensure adequate protections are
provided for trees being transplanted. |
HY2009/19 |
·
Road
works at ·
Bored
piling (Land) ·
Pre-drilling
works for bored pile and Diaphragm wall ·
D-wall
Construction (North & South Section) ·
Guide
wall construction for D-wall / Barrette at North side ·
Construction
works for Box Culvert T1 ·
Marine
Piling ·
Construct
ion of socket-H pile ·
Construction
works for Culvert U1 ·
Construction
of 1500f drainage pipe ·
Construction
of Pile caps & columns (Land) ·
Dismantling
of marine platform ·
Demolition
of parapet at IEC Link ·
Construction
of Pile caps & columns (Marine) ·
Cut
& Cover Tunnel sheet piling works ·
Construction
of dewatering well for Cut & Cover Tunnel |
·
Noise
level shall be controlled by reducing the pilling operation rate. ·
Noise
barrier shall be implemented. ·
Dust
control during dust generating works ·
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. |
HK2009/01 |
·
Backfilling
works on top of SCL protection works. ·
Jet
grouting to HKCEC new extension foundation. ·
Plant
mobilization for installation of pre-bored H-pile works at Stage 1b &
Stage 2 ·
Pre-drilling
works for CWB (Stage 2). |
·
Noise
level shall be controlled by reducing no. of plants working in parallel. ·
Well
maintained enclosures for grouting mixing plants. ·
Provide
protection works and adequate drainage system to ensure no direct discharge
into public drainage system or the sea. ·
Dust
control during dust generating works |
HK/2009/02 |
·
Trimming
of bored pile head and blinding for the base slab construction at tunnel
portion 1. ·
Waterproofing
installation for the base slab at tunnel portion 1. ·
Rebar
fixing and base slab concreting at Tunnel Portion 1. ·
G.I.
and remove the temporary sheetpile wall at WCR2 ·
Diaphragm
wall construction for Eastern Bulkhead Panel BHP3 and BHP7. ·
Bulkhead
at Bay 14 of Box Culvert “O” and stage 2 diversion of uncharted drainage
works at Box culvert “O”. ·
Trial
excavation, footpath set back, UU diversion, tree transplantation,
reprovision of street furniture and preparation works for Hung Hing Road
Diversion Stage 1. ·
Caisson
seawall precast unit 2X in-situ work on flat-top barge. |
·
Well
maintain the enclosures for grouting and bentonite mixing plants. ·
Dust
control during dust generating works ·
Provision
of protection to ensure no runoff out of site area or direct discharge into
public drainage system. |
HK/2010/06 |
·
Construction
of Pre-cast Unit in |
·
Air
pollution control during transportation |
10.0.3. The
construction works of Contract no. 04/HY/2006 – Reconstruction of Bus Terminus
near